You are almost done on site when the client wants you to do another wall too. It seems easy, but materials, labor and time may be affected. If you only talk about it during invoicing, you might find that neither party clearly agreed to these points.

Make the client aware of the change early, while they still have the flexibility to decide what to do and how to do it. That avoids arguing about the cost after completion. The change order should reflect what changed, its cost impact and its schedule effect.

Which details belong in a change order?

Record the project, original contract, change-order number, date issued, reasons and affected drawing or specification version. Indicate the relevant item in the original contract, quote or drawing.

Instead of saying “site adjustment,” say what is added, omitted or revised. Use useful sketches, field reports, supplier quotes, photos or other records. Indicate the location, quantity and specification so someone who was not there can understand the difference.

Show the original contract sum, net previously approved changes, contract sum before this change, current addition or deduction and new contract sum. Record the increase or decrease in time and the new completion date.

  • Project, contract, change number, date, reason
  • Detailed added, omitted or revised scope
  • Current and new contract sum
  • Schedule adjustment, exhibits, approvals

Worked change-order example

These examples are hypothetical. Follow the contract for tax and pricing, and include deductions as well as additions. In the corridor-painting example, additional labor is 6 hours × 150 yuan/hour = 900 yuan. Paint and consumables add 320 yuan, while cancelling the original decorative trim gives a 120 yuan deduction. The net increase is 1,100 yuan, plus an extension of 1 working day confirmed by both sides.

In a separate dollar example, the original contract is $180,000 and net changes approved to date add $12,000. The contract sum before this change is therefore $192,000. The current change adds $4,800 demolition, $9,200 materials, $6,400 labor and $1,600 equipment, totaling $22,000. Subtract the original $3,000 finish allowance for a net increase of $19,000. The new contract sum is $180,000 + $12,000 + $19,000 = $211,000.

If the new work adds 5 calendar days and that effect is approved under the agreement, document the extension and new completion date. This dollar example does not include treatment of tax, markup rules, bonds, insurance or other project-specific costs. It does not cover every settlement requirement.

  • Additions: $4,800 + $9,200 + $6,400 + $1,600 = $22,000
  • Net change: $22,000 − $3,000 omitted allowance = $19,000
  • New contract: $180,000 + $12,000 + $19,000 = $211,000
  • Time change: +5 calendar days with a new completion date, if approved under the agreement
A contractor and homeowner discussing different tile choices

How should cost and time be supported?

Follow the contract's pricing method: an agreed lump sum, verified unit prices, time-and-materials pricing or another defined basis. List labor hours and rates, material quantities and quotes, equipment, subcontracting, credits, overhead and permitted markup. Do not charge again for something already in the original scope just because it appears in a change order. Can old materials be returned? What have you already spent on cancelled work?

Do not pick a schedule change at random. Document when information arrived or site access became available, the effect on the critical path and the measures considered to minimize delay. Do not assume that a no-extra-cost change has no time impact, or that a price change automatically justifies extra time.

  • Contractual pricing method and cost breakdown
  • Credits for work or allowances removed
  • Affected schedule activity and relevant dates
  • Separate conclusions on price and time

How does a change reach progress billing?

Avoid mixing pending changes into the approved contract sum. When the required sign-off or other valid authorization under the agreement is in place, update the approved change log and revised sum. Add the work to the schedule of values or continuation sheet as the project requires. Reference CO-003 on the invoice or payment application. Keep the original quote, change order, approvals, updated schedule, payment application, invoice and payment documents, so the reviewer can understand why the amount entered the contract and the level of completion.

Do not include the same change in an original item and then invoice it as a separate change. Whether pending work can enter progress billing depends on the contract. Do not treat a pending amount as approved contract value.

  • Pending changes stay outside approved contract value
  • Authorized changes are reflected in the approved change log
  • Schedule of values records changed work only once
  • Billing traces back to scope, price, time and approval

Describe the difference from the original scope

Describe the original scope, then what the client wants to add, drop or replace. Specify the location, quantity, material and delivery standard, with drawings or their version where applicable. “Additional work on site” does not clarify which original work stays and what changes.

For example, the original scope is to paint two living-room walls. The change adds one corridor wall, about 12 square meters, in the same color. Describe how measurements and site conditions will be verified and which original work remains.

Cancelling or substituting work, or reducing the scope, may reduce charges or change the schedule. Show additions and deductions, but do not charge for both the original and replacement work. Consider how different materials affect results, delivery time and warranty. Make a departure from the original agreement clear in the project records.

Include both additions and credits

In a yuan example, add 6 hours of labor at 200 yuan/hour and 500 yuan of materials. Remove 300 yuan of planned work that has not been done. The net increase before tax is 1,400 yuan. A detailed calculation is easier to check than only the net result.

In a different quantity-based example, 6 units at 200 total 1,200, additional labor is 500, and removed work gives a 300 credit. The net increase before tax or other agreed adjustments is 1,400. Here, 1,200 is the quantity-based addition, not the labor charge in the previous example.

Illustrative changeAmount
Six additional units at 2001,200
Additional labor500
Credit for removed work−300
Net change before tax1,400

Explain the effect on timing and other work

A change may mean new material orders, waiting for specialists, a return to site, rework or delaying dependent tasks. Explain the likely additional time, the activity or phase affected, whether the client needs to decide by a certain date, and any effect on permits, subcontractors, procurement or acceptance requirements. Include what affects the client's decision without unrelated internal details.

If you expect no time impact, say so. If it is still unresolved, say what information or quote is needed and when you will report next. Do not put an unsupported zero-day delay in the document just to get a quick signature.

Obtain approval from the right person

If the requester is not the decision maker, identify who can commit the client and approve charges under the project contract. Confirm scope, amount and time before proceeding, and record the approved version, date and person. A request on site does not necessarily meet the contract's authorization requirements.

Turn a verbal request into a written request. Ask the authorized person to confirm scope, charges and time. Whether a chat message saying “yes” is authorization depends on the contract, the chat content and the sender's authority. Keep scope, charges and time in the same retrievable record.

For example: “Change CO-003: add painting to the corridor wall, with a net increase of 1,100 yuan and an extension of 1 working day. Please confirm the added scope, charges and revised completion arrangements. Once confirmed, we will proceed accordingly.”

For genuine urgent safety or protective work, follow the applicable contract and legal process. Notify promptly, retain site records and complete the confirmation as soon as possible. Do not treat every urgent client request as a special case without approval.

Keep the number, date, project reference and approver tied to the same version. Do not leave site staff using an old drawing, procurement using new quantities and billing using another amount. Make clear the current version for work and billing.

Carry the change through the project records

Once approved, update the scope, budget, schedule, purchase-order and billing records. The project log should record the original contract sum, each approved change and the new total. Reference the change number on the invoice. For a staged project, integrate the amounts into the appropriate contract value and schedule-of-values structure, based on actual approval and completion, so the reviewer can follow the current payment application.

Keep pending and cancelled items, and those still under discussion, in separate statuses instead of mixing them into the formal total. Reconcile the change log with payment records at closeout to minimize repeated searches for payment status.

When there is disagreement, return to the decision

Look at the client's request, what was approved and what was delivered. Is the issue about price, scope or authority? Look for the communications and documents rather than relying on memory of the site conversation. Follow the contract's dispute procedure where needed.

Price future additions and obtain approval early. Do not let the final invoice be the first full record of the extra work.

Questions you may still have

Is a change order the same as an estimate?

No. An estimate is about likely cost. A change order documents a contract change approved under the agreement. An estimate still under discussion is not approval.

Can a construction change order reduce the price?

Yes. It can increase, reduce or leave the contract sum unchanged. Document additions and deductions without billing for both the original and replacement work.

Should pending change work appear in progress billing?

It depends on what the contract allows. Keep pending work separate from approved contract value, and do not show a proposed amount as approved.